To Link Activities to Components
- From the ConstructSim menu, select The . 4D Autolinking dialog opens.
-
Click New.
The Matching Rule Setup dialog opens and is used to link the components to the schedule.
- In the Rule Name field, give the rule a name. Set Rule Match to Window 1 substring of Window 2.
- In the Window 1 section, set Name to Components and Type to Organizer. In the Attributes/Fields box, select Name and click Add.
- In the Window 2 section, set Name to Schedule and Type to ProjectTask. In the Attributes/Fields box, select Activity Description and click Add.
- Click OK.
-
In the 4D Autolinking dialog, click Run.
In the Schedule dialog, icons that show a fold on the bottom right corner designate the tasks that are linked to the schedule.